Can our Vacaville solar permit cover a new main panel too?
Yes. The city issues residential rooftop solar permits of any size online, and a solar permit automatically includes a main panel change-out if one is wanted. Decide before you apply, since refunds are generally not available for solar permits issued online. A C-10 contractor's load calculation shows whether the existing panel would do.
The label inside our panel is unreadable. Will that hold up solar?
It can. Vacaville's solar submittal list requires the nameplate bus bar rating on the line diagram. Where that rating is no longer available, the plans need a letter from a registered third party such as UL confirming its evaluation and recertification of the panel, or the service panel can be replaced as part of the same job.
Do we buy power from PG&E or MCE in Vacaville?
PG&E. MCE lists Fairfield, Benicia, Vallejo and unincorporated Solano County among the communities it serves, but not Vacaville, so PG&E both supplies and delivers the electricity here. It is also the utility an electrician coordinates with when a service is disconnected, reconnected or upsized.
Does a bigger electrical service in Vacaville need more than a permit?
Sometimes. The city's service checklist asks for an AIC letter on available fault current once a service reaches 250 amps, and sends services of 400 amps or more, and any multiple-meter installation, through city plan check. A single-family service disconnect must be at least 100 amps.
Our street is on Cal Fire's new hazard map. Does that change solar on our roof?
The setbacks already apply. Cal Fire's recommended map for Vacaville's local responsibility area reached the city on February 24, 2025, and the zones mostly affect building materials and defensible space. For rooftop solar, the city's submittal rules already apply the setbacks in Cal Fire's Solar Photovoltaic Installation Guidelines to every residential rooftop array, inside a mapped zone or not.
How long does Vacaville take to review a solar or EV charger plan?
The city's published review table gives residential solar and EV charger plans a maximum of two working days for the first review and ten for each resubmittal, with comments sent within three days after every department finishes. Vacaville offers no expedited plan review, and reviews beyond the second plan check carry an hourly fee with a two-hour minimum. A complete first submittal, with the bus bar rating and any load calculation on the line diagram, is what keeps a job on the short track.