Do I need a sewer lateral inspection to sell my house in Mill Valley?
Inside city limits, yes. A sale has been one of the inspection triggers since June 2, 2015. A plumbing contractor runs a camera through the lateral and submits the city's report form, the video link, a site sketch and the fee to Public Works. A lateral installed or fully replaced within 20 years, or repaired within three, is exempt if you can prove it.
We're adding a powder room. Does the whole sewer line have to be replaced?
Probably. The city's rule is that any work increasing the number of plumbing fixtures means replacing the lateral, unless you can show it is a tightline pipe, steel or plastic, in good condition. Clay laterals do not qualify, so they are replaced, with the proper permits. A camera inspection early in design shows which case you are in.
Who pays to fix the sewer pipe under the street in front of my Mill Valley house?
The owner. Inside city limits the Municipal Code puts the lateral on the property owner all the way to the city main, including the section in the right-of-way and the fitting where it branches off the main. Work in the street also needs a permit from Public Works for the right-of-way portion.
Our house sits below the road. Why does the plumber say we need a pump?
Because waste cannot flow uphill to a sewer that sits higher than the house. SASM allows an individual sewage ejector pump only through a special application where gravity service is not feasible, requires two pumps for a whole-house system, and inspects the pump station and the pressure line. The city or county may require its own building permit for the pump and electrical work too.
Is there any help paying for a new lateral in Mill Valley?
SASM's Cash for Sewers program reimburses part of the cost for residents required to replace a lateral because of a capital improvement project, part of the cost of a camera inspection, and a larger share for lower-income households. Every participant needs a Certificate of Compliance from their sewer district, which a building permit does not replace, and the caps can change as the fund runs down.